Category Archives: Painting

Cape Coral Home Exterior Repaint

Our office was recently contacted by a Cape Coral homeowner in search of a painting company to restore their home’s worn paint. Upon meeting with the client, we discussed the scope of work, color selections, and options for paint. Once contracted, our painting division went to work restoring the curb appeal of this Cape Coral home. Once the perimeter of the home was trenched, we pressure washed the home to remove any surface contaminates and debris. A coat of masonry sealer was applied to all stucco surfaces, and any cracks were repaired with elastomeric patching compound. Additionally, if any caulk at the home’s windows and doors was worn, we removed and replaced as needed.

Sherwin Williams paint products were selected, and the paint was applied using a brush and roll technique. With their home freshly repainted, our customer can enjoy peace of mind with a 10 year limited labor and materials warranty from Sherwin Williams. As Southwest Florida’s premier painting company, we strive to exceed client expectations. We couldn’t be happier with how this home turned out, and are blessed with the opportunity to serve another wonderful resident of our community.

Fort Myers Home Receives New Tile Roof, Gutters, and Exterior Repaint

Our office recently had the pleasure of transforming a wonderful homeowner’s residence in Fort Myers Florida. We were initially contacted to inspect the home’s aged roof, which was found to have normal wear and tear for its age. After speaking with the homeowners, they had sought to modify the look of the home as well with a completely new color scheme.

Once contracted our teams went to work on the home’s roof. We removed the existing tile and underlayment, and disposed of it in accordance with our local code regulations. The roof’s decking was inspected with any deteriorated or damaged material replaced accordingly. Once complete, the decking was re-nailed to meet hurricane mitigation code, and the appropriate tile underlayment was applied to the entire roofs surface. New 26 GA pre-painted drip edge flashing was applied to the entire perimeter of the roof, new 26 GA galvalume valley metal was installed in all valleys, as well as the appropriate vents and closure metal with lead flashing installed around all plumbing stacks. New tile was then installed to the entire roof per manufacturer specifications, which also carries a 5 year workmanship warranty on the tile application, along with the manufacturer’s product warranty. Following the completion of the roofing structure, our team installed new 6″ aluminum seamless gutters with the appropriate downspouts, and splashguards.

As the homeowners wanted to transform the exterior aesthetic of their home, we used Sherwin Williams paint products to paint this beautiful home in their Essential Grey color along with Polished Concrete for the trim. You can view photos of this beautiful transformation below. We would also like to thank the homeowners for trusting our company with their roofing and painting needs. We are thrilled with the final product and are thankful for the opportunity to exceed our client’s expectations!

 

 

If you’re a homeowner in Southwest Florida in need of roofing or painting services, we welcome the opportunity to educate you of your options and earn your business. Contact our Fort Myers office today at (239) 652-5784 or fill out the form below to learn more!

    By clicking "submit", I consent to join the email list and receive SMS from First Service CGC, with access to our latest offers and services. Message and data rates may apply. Message frequency varies. More details on this are in our Privacy Policy & Terms & Conditions.Text "HELP" for help or contact us at (239) 652-5784. Text "UNSUBSCRIBE" to cancel.

Executive Dining & Buffet Room Remodel At The Westin Cape Coral Resort At Marina Village

Throughout Southwest Florida, First Service known to have a strict attention to detail with each service we provide, for every project. Having served the general construction needs of Tarpon Point for many years, we welcomed the opportunity to serve the construction needs of the Westin Cape Coral Resort at Marina Village, when an area of their facility needed remodeled. Once presented with the details to remodel the executive dining and buffet area, we jumped at the opportunity to exceed the expectations of this renowned Cape Coral resort.

Once the facilities demolition work was completed, our team at First Service went to work building a wall across the width of the room. We strategically placed the wall to center it between the exterior door and fire alarm handle, which allowed for an efficient use of the available space. Soundproof insulation was installed within all walls, and drywall was hung and completed with a level 4 finish. Accompanying columns and trim were also installed and matched to the wall.

Between the new wall we installed a sheetrock ceiling, while also raising the acoustic ceiling and grid of the executive dining space to the highest point possible with the existing ductwork and air conditioning equipment. Once complete we also framed in all plumbing not enclosed in the new ceiling height with a sheetrock chase, and installed stain grade crown baseboard and molding to match the existing trim of the restaurant as much as possible.

Once all work was completed, our painting division cleaned and painted the entire space including all flat ceilings to properly finish the project and provide the refined, modern look Tarpon Point is famous for. Our team’s dedication, experience, and unique skillset allowed us to efficiently and effectively exceed our customers expectations on this project, and we couldn’t be happier with the final product!

Estero FL Home Receives A New Roof, Gutters, and An Exterior Repaint

At First Service, we take pride in exceeding the expectations of our customers. We recently had the opportunity to completely transform the exterior of a customers home in Estero Florida. Our team started by replacing the existing roofing structure on this home. After the existing roof was removed and properly prepared for the new roofing materials, we installed Boral’s Espresso Blend roofing tile. When our roof construction was complete, our team also formed and installed new 6″ aluminum seamless gutters to the first story of the home. This ensured that water would be properly diverted from the home.

Once concluded, our painting division paid this residence a visit. Using Sherwin Williams paint products, we repainted the exterior of this home per our customer’s color choices. The end result was stunning and we’re blessed that our company was chosen to help transform this home from top to bottom!

Fort Myers Home Tile Re-Roof & Exterior Repaint

Our office recently had the great pleasure of serving a homeowner within the Shadow Wood Preserve community. The customer contracted us to replace their homes existing tile roof, and repaint the exterior of the residence.

Roof Replacement Scope Of Work

Upon beginning we removed the existing tile and underlayment from the roof, and properly disposed of the material in accordance with local code. Once the roof’s decking was properly inspected and replaced where applicable, we installed new tile underlayment to the entire surface of the roof. New 26 GA drip edge flashing, galvalume valley metal, and the appropriate vents, stacks, and flashing were also installed on the roof. Once properly prepared, the new tile roof system was installed with the appropriate foam adhesion and/or two screw fastener application system (per manufacturer specifications).

Exterior Repaint Scope Of Work

Using Sherwin Williams paint products our painting division went to work to transform the exterior of this beautiful Fort Myers Home. Our standard paint procedure implemented consist of the following referenced items below:

  1. TRENCH AROUND PERIMETER OF HOME 1 TO 3 INCHES.
  2. PRESSURE WASH EXTERIOR FREE OF DIRT AND FOREIGN MATERIAL
  3. APPLY ONE COAT OF MASONRY SEALER TO STUCCO SURFACES
  4. SEAL MASONRY CRACKS, IF PRESENT, WITH ELASTOMERIC PATCHING COMPOUND
  5. INSPECT CAULK AT WINDOWS AND DOORS, IF DETERIORATED REMOVE AND REPLACE AS NEEDED
  6. APPLY ONE COAT OF SW DURATION SATIN PAINT, USING BRUSH AND ROLL TECHNIQUE, TO STUCCO WALLS, CEILINGS, FASCIA, SOFFIT, BANDS & TRIM
  7. APPLY ONE COAT OF SW DURATION SEMI-GLOSS PAINT TO THE EXTERIOR SIDE OF ENTRY & GARAGE DOORS 8. COLORS TO BE SELECTED BY OWNER

With a strict attention to detail and a drive to provide both an exceptional product and exemplary customer service, our teams completed the work contracted in record time. As always our customer can rest easy knowing that their home is protected by a roof from First Service! We would like to take this time to thank our customer for the opportunity, and our staff for all of their hard work on this project.

Estero Florida Tile Roof Replacement, Gutter Install, and Exterior Paint

Our office was recently contacted by a homeowner in Estero Florida with a roof leak that required a temporary repair until the roof could be replaced. Our team inspected the roof and when appropriate, replaced the residences roofing structure using Boral’s Barcelona 900 tile in their stone light brown color. Once the home received its new roof, our team also replaced the gutter system with new 6″ aluminum seamless gutters and wedges.

As the top half of the home had undergone a complete transformation, our clients felt that the exterior finish of the home was in need of work as well. Our painting division was called in to repaint the exterior of this residence using Sherwin Williams paint products. Not only has this client’s home increased its curb appeal, but they can also rest easy knowing that their home is protected for years to come with an expertly installed roofing system from First Service!

Special Materials:

  • Tile Manufacturer: Boral
  • Style (Profile): Barcelona 900
  • Color: Stone Light Brown
  • Drip Edge Color: White
  • EXTERIOR REPAINT PAINT MANUFACTURER: SHERWIN WILLIAMS PAINT PRODUCTS
  • PRIMER: LOXON MASONRY CONDITIONER
  • STUCCO SURFACES, CEILINGS: SW DURATION SATIN
  • DOORS: SW DURATION SEMI-GLOSS

Re-Roof Scope Of Work:

Provide labor and materials to complete the following:

  • Remove existing tile and underlayment and dispose of in accordance with local code.
  • Inspect existing decking. Damaged or deteriorated decking will be replaced on a unit price basis.
  • Re-nail decking to meet hurricane mitigation code.
  • Install tile underlayment to entire roof surface.
  • Install new 26 GA pre-painted drip edge flashing to entire roof perimeter.
  • Install new 26 GA galvalume valley metal in all valleys.
  • Install 26 GA galvalume kitchen and dryer vents.
  • Install 26 GA eave closure metal.
  • Install new lead flashing around all plumbing stacks.
  • Install a new tile roof system with foam adhesion and or two screw fastener application system as per manufacturer specifications.
  • Provide (2) year workmanship warranty on tile application.
  • Provide manufacturers warranties.

Gutter Install Scope Of Work:

Provide labor and material to complete the following:

  • Remove and dispose of the existing gutters and downspouts.
  • Install up to 205LF of new desert sand 6″ aluminum seamless gutters with wedges.
  • Install up to (6) downspouts, (3) small downspouts, (15lf) splash guards, (4) miters, (4lf) of kickout extensions to match the existing layout.
  • Jobsite will be cleaned of all work-related debris upon completion.

Exterior Paint Scope Of Work:

  1. TRENCH AROUND PERIMETER OF HOME 1 TO 3 INCHES.
  2. PRESSURE WASH EXTERIOR FREE OF DIRT AND FOREIGN MATERIAL
  3. APPLY ONE COAT OF MASONRY SEALER TO STUCCO SURFACES
  4. SEAL MASONRY CRACKS, IF PRESENT, WITH ELASTOMERIC PATCHING COMPOUND
  5. INSPECT CAULK AT WINDOWS AND DOORS, IF DETERIORATED REMOVE AND REPLACE AS NEEDED
  6. APPLY ONE COAT OF SW DURATION SATIN PAINT, USING BRUSH AND ROLL TECHNIQUE, TO STUCCO WALLS, CEILINGS, FASCIA, SOFFIT, BANDS & TRIM
  7. APPLY ONE COAT OF SW DURATION SEMI-GLOSS PAINT TO THE EXTERIOR SIDE OF ENTRY & GARAGE DOORS
  8. A 10-year limited labor and materials warranty will be issued by Sherwin Williams.

Tile Roof Replacement, Gutter Installation, and Exterior Repaint For Ft. Myers Home

At First Service, we are blessed with the opportunity to work with many amazing clients. This home in Fort Myers, FL is no exception. The new homeowners within the Gateway community wanted a new look for their home, and chose our company to help. Our roofing division replaced the home’s damaged roof with a new Boral tile roof using their Barcelona 900 tile in their mountain blend colorway. Additionally, our team also installed new 6″ white aluminum seamless gutters to properly divert water off of the home’s roof. Once complete with the roof and gutter system, our painting division stepped in using Sherwin Williams premium paint products and repainted the exterior of this beautiful home.

This project turned out great and our client’s new home certainly increased its curb appeal. What a beautiful home!

Special Materials:

  • Tile Manufacturer: Boral
  • Style (Profile): Barcelona 900
  • Color: Stone Mountain Blend
  • Drip Edge Color: Grey
  • EXTERIOR REPAINT PAINT MANUFACTURER: SHERWIN WILLIAMS PAINT PRODUCTS
  • PRIMER: LOXON MASONRY CONDITIONER
  • STUCCO SURFACES, CEILINGS: SW DURATION SATIN
  • DOORS: SW DURATION SEMI-GLOSS

Re-Roof Scope Of Work:

Provide permit, labor, and materials to complete the following:

  • Remove existing tile and underlayment and dispose of in accordance with local code.
  • Inspect existing decking. Damaged or deteriorated decking will be replaced on a unit price basis.
  • Re-nail decking to meet hurricane mitigation code.
  • Install tile underlayment to entire roof surface.
  • Install new 26 GA pre-painted drip edge flashing to entire roof perimeter.
  • Install new 26 GA galvalume valley metal in all valleys.
  • Install 26 GA galvalume kitchen and dryer vents.
  • Install 26 GA eave closure metal.
  • Install new lead flashing around all plumbing stacks.
  • Install a new tile roof system with foam adhesion and or two screw fastener application system as per manufacturer specifications.
  • Provide five (5) year workmanship warranty on tile application. Provide manufacturers warranties.

Gutter Installation Scope Of Work:

Provide labor and material to complete the following:

  • Install new 120 LF 6″ white aluminum seamless gutters around the entire perimeter eave of the house.
  • Install “3” new white downspouts in locations approved by the homeowner.
  • Install “2” corner strip miters, and “2” outside miters.
  • Install “2” splashed guards, one on each inside corner at the base of each roof valley.

Exterior Paint Scope Of Work:

  1. TRENCH AROUND PERIMETER OF HOME 1 TO 3 INCHES.
  2. PRESSURE WASH EXTERIOR FREE OF DIRT AND FOREIGN MATERIAL
  3. APPLY ONE COAT OF MASONRY SEALER TO STUCCO SURFACES
  4. SEAL MASONRY CRACKS, IF PRESENT, WITH ELASTOMERIC PATCHING COMPOUND
  5. INSPECT CAULK AT WINDOWS AND DOORS, IF DETERIORATED REMOVE AND REPLACE AS NEEDED
  6. APPLY ONE COAT OF SW DURATION SATIN PAINT, USING BRUSH AND ROLL TECHNIQUE, TO STUCCO WALLS, CEILINGS, FASCIA, SOFFIT, BANDS & TRIM
  7. APPLY ONE COAT OF SW DURATION SEMI-GLOSS PAINT TO THE EXTERIOR SIDE OF ENTRY & GARAGE DOORS

Hilton Garden Inn Commercial Exterior Repaint

Close to the Lakeland airport, off of Route 570, this hotel wanted to transform the exterior of their facility to improve its curb appeal. Our company was hired to do just that! Once contracted, our painting division went to work to complete a full exterior repaint of the hotel just in time for Summer and incoming guests of the hotel. We used the finest Sherwin Williams paint products to produce a vibrant, deep colorway across the building. We love the colors chosen and are thrilled with how this commercial paint project turned out!

Project Information:

  • PAINT MANUFACTURER: SHERWIN WILLIAMS PAINT PRODUCTS
  • PRIMER: LOXON MASONRY CONDITIONER CLEAR
  • STUCCO SURFACES: SW SUPER PAINT SATIN
  • DOORS: SW SUPER PAINT SEMI-GLOSS

EXTERIOR PAINT SCOPE OF WORK:

  1. TRENCH AROUND PERIMETER OF BUILDING 1 TO 3 INCHES.
  2. PRESSURE WASH EXTERIOR FREE OF DIRT AND FOREIGN MATERIAL
  3. APPLY A CONSISTENT COAT OF SEALER TO ALL SURFACES TO ENSURE FINISH COAT HAS PROPPER ADHESION TO EXSISTING SURFACES.
  4. CAULK WHERE NECESSARY AROUND DOORS, WINDOWS, AND J CHANNEL. SEAL ANY CRACKS DUE TO EXPANSION AND SHRINKING FOR THE EXTERIOR ELEMENTS, AS NEEDED, WITH ELASTOMERIC PATCHING COMPOUND
  5. APPLY A CONSISTENT COAT OF FINISH TO ALL PREVISLY PAINTED SURFACES (HARDY BOARD SURFACES). WALLS AND EXTERIOR SIDE OF PREVIOSOULY PAINTED DOORS.
  6. COLORS TO MATCH EXSISTING.

Fort Myers Tile Roof Replacement & Repaint

Our office recently had the pleasure of serving the needs of a wonderful customer within the Gateway Greens community in Fort Myers Florida. Upon being contacted our team visited the residence to perform a roof inspection. With extensive damage on the roof, it was later determined that Hurricane Irma was the root cause of these damages and in order to properly repair, the home would need to receive a complete roof replacement. Once the project was approved we went to work removing the existing tile roof. Following the removal of the tile and installation of the appropriate underlayment, our team installed Boral’s Barcelona 900 tile in their gold dust color. Our team completed the roof and installed a new aluminum seamless gutter system as well to finish the project.

After our roofing team was complete, our painting division mobilized and completed a full exterior repaint using Sherwin Williams paint products. The end result turned out amazing and our customer’s selections beautifully transformed the exterior of this home!

Special Materials:

  • Tile Manufacturer: Boral
  • Style (Profile): Barcelona 900
  • Color: Gold Dust
  • Drip Edge Color: White

Re-Roof Scope Of Work:

Provide permit, labor, and materials to complete the following:

  • Remove existing tile and underlayment and dispose of in accordance with local code.
  • Inspect existing decking. Damaged or deteriorated decking will be replaced on a unit price basis.
  • Re-nail decking to meet hurricane mitigation code.
  • Install tile underlayment to entire roof surface.
  • Install new 26 GA pre-painted drip edge flashing to entire roof perimeter.
  • Install new 26 GA galvalume valley metal in all valleys.
  • Install 26 GA galvalume kitchen and dryer vents.
  • Install 26 GA eave closure metal.
  • Install new lead flashing around all plumbing stacks.
  • Install a new tile roof system with foam adhesion and or two screw fastener application system as per manufacturer specifications.
  • Provide five (5) year workmanship warranty on tile application.
  • Provide manufacturers warranties.

Gutter Installation Scope Of Work:

Provide labor and material to complete the following:

  • Remove and dispose of the existing gutters and downspouts.
  • Install up to 60LF of new white 6″ aluminum seamless gutters.
  • Install up to (3) downspouts to match existing layout.
  • Jobsite will be cleaned of all work-related debris upon completion.

Exterior Repaint:

  • PAINT MANUFACTURER: SHERWIN WILLIAMS PAINT PRODUCTS
  • PRIMER: LOXON MASONRY CONDITIONER
  • STUCCO SURFACES: SW SUPER PAINT SATIN
  • DOORS: SW SUPER PAINT SEMI-GLOSS
  1. TRENCH AROUND PERIMETER OF HOME 1 TO 3 INCHES.
  2. PRESSURE WASH EXTERIOR FREE OF DIRT AND FOREIGN MATERIAL
  3. APPLY A CONSISTENT COAT OF MASONRY SEALER TO STUCCO SURFACES
  4. CAULK WHERE NECESSARY AROUND DOORS, WINDOWS, AND J CHANNEL. SEAL MASONRY CRACKS, AS NEEDED, WITH ELASTOMERIC PATCHING COMPOUND
  5. APPLY A CONSISTENT COAT OF FINISH PAINT TO STUCCO WALLS AND EXTERIOR SIDE OF ENTRY & GARAGE DOORS

 

Condo Association Roof Replacement, Gutter Installation, and Re-Paint

Located in beautiful Cape Coral Florida, the Victoria Harbor Condominium association had contacted our office to repair damage that their facility experienced during Hurricane Irma. Following an inspection it was determined that the storm had caused extensive damage to the waterfront roofing structure resulting in a need for a complete roof replacement. Once approved, our roofing division went to work removing the existing roof and replacing it with new Eagle Malibu tile in their Riviera color. Once completed, our gutter and painting divisions stepped in to help give the building a beautiful new look. The finished product turned out amazing and our client couldn’t be happier with how everything turned out!

Special Materials

  • Tile Manufacturer: Eagle
  • Style (Profile): Malibu
  • Color: Riviera
  • Drip Edge Color: White

Re-Roof Scope Of Work

Provide permit, labor, and materials to complete the following:

  • Remove existing tile and underlayment and dispose of in accordance with local code.
  • Inspect existing decking. Damaged or deteriorated decking will be replaced on a unit price basis.
  • Re-nail decking to meet hurricane mitigation code.
  • Install tile underlayment to entire roof surface.
  • Install new 26 GA pre-painted drip edge flashing to entire roof perimeter.
  • Install new 26 GA galvalume valley metal in all valleys.
  • Install 26 GA galvalume kitchen and dryer vents.
  • Install 26 GA eave closure metal.
  • Install new lead flashing around all plumbing stacks.
  • Install a new tile roof system with foam adhesion and or two screw fastener application system as per manufacturer specifications.
  • Provide five (2) year workmanship warranty on tile application.
  • Provide manufacturers warranties.
  • Fabricate and install 24-gauge Kynar painted metal to all parapet walls for metal roof repair.
  • Cap to match building layout.
  • Attach with 5v neoprene screws. 1 foot on center along each side. This metal cap will provide a lifetime of protection to the top of the parapet walls.

Provide labor and material to complete the following gutters:

  • Remove and dispose of the existing gutters and downspouts.
  • Install up to 25LF of new white 6″ aluminum seamless gutters on the first story.
  • Install up to 135LF of new white 6″ aluminum seamless gutters on the second story.
  • Install up to (4) 2-story downspouts, (1) 1-story downspout, (5) miters to match the existing layout.
  • Jobsite will be cleaned of all work-related debris upon completion.