Fort Myers Home Tile Re-Roof & Exterior Repaint

Our office recently had the great pleasure of serving a homeowner within the Shadow Wood Preserve community. The customer contracted us to replace their homes existing tile roof, and repaint the exterior of the residence.

Roof Replacement Scope Of Work

Upon beginning we removed the existing tile and underlayment from the roof, and properly disposed of the material in accordance with local code. Once the roof’s decking was properly inspected and replaced where applicable, we installed new tile underlayment to the entire surface of the roof. New 26 GA drip edge flashing, galvalume valley metal, and the appropriate vents, stacks, and flashing were also installed on the roof. Once properly prepared, the new tile roof system was installed with the appropriate foam adhesion and/or two screw fastener application system (per manufacturer specifications).

Exterior Repaint Scope Of Work

Using Sherwin Williams paint products our painting division went to work to transform the exterior of this beautiful Fort Myers Home. Our standard paint procedure implemented consist of the following referenced items below:

  1. TRENCH AROUND PERIMETER OF HOME 1 TO 3 INCHES.
  2. PRESSURE WASH EXTERIOR FREE OF DIRT AND FOREIGN MATERIAL
  3. APPLY ONE COAT OF MASONRY SEALER TO STUCCO SURFACES
  4. SEAL MASONRY CRACKS, IF PRESENT, WITH ELASTOMERIC PATCHING COMPOUND
  5. INSPECT CAULK AT WINDOWS AND DOORS, IF DETERIORATED REMOVE AND REPLACE AS NEEDED
  6. APPLY ONE COAT OF SW DURATION SATIN PAINT, USING BRUSH AND ROLL TECHNIQUE, TO STUCCO WALLS, CEILINGS, FASCIA, SOFFIT, BANDS & TRIM
  7. APPLY ONE COAT OF SW DURATION SEMI-GLOSS PAINT TO THE EXTERIOR SIDE OF ENTRY & GARAGE DOORS 8. COLORS TO BE SELECTED BY OWNER

With a strict attention to detail and a drive to provide both an exceptional product and exemplary customer service, our teams completed the work contracted in record time. As always our customer can rest easy knowing that their home is protected by a roof from First Service! We would like to take this time to thank our customer for the opportunity, and our staff for all of their hard work on this project.

Estero Florida Tile Roof Replacement, Gutter Install, and Exterior Paint

Our office was recently contacted by a homeowner in Estero Florida with a roof leak that required a temporary repair until the roof could be replaced. Our team inspected the roof and when appropriate, replaced the residences roofing structure using Boral’s Barcelona 900 tile in their stone light brown color. Once the home received its new roof, our team also replaced the gutter system with new 6″ aluminum seamless gutters and wedges.

As the top half of the home had undergone a complete transformation, our clients felt that the exterior finish of the home was in need of work as well. Our painting division was called in to repaint the exterior of this residence using Sherwin Williams paint products. Not only has this client’s home increased its curb appeal, but they can also rest easy knowing that their home is protected for years to come with an expertly installed roofing system from First Service!

Special Materials:

  • Tile Manufacturer: Boral
  • Style (Profile): Barcelona 900
  • Color: Stone Light Brown
  • Drip Edge Color: White
  • EXTERIOR REPAINT PAINT MANUFACTURER: SHERWIN WILLIAMS PAINT PRODUCTS
  • PRIMER: LOXON MASONRY CONDITIONER
  • STUCCO SURFACES, CEILINGS: SW DURATION SATIN
  • DOORS: SW DURATION SEMI-GLOSS

Re-Roof Scope Of Work:

Provide labor and materials to complete the following:

  • Remove existing tile and underlayment and dispose of in accordance with local code.
  • Inspect existing decking. Damaged or deteriorated decking will be replaced on a unit price basis.
  • Re-nail decking to meet hurricane mitigation code.
  • Install tile underlayment to entire roof surface.
  • Install new 26 GA pre-painted drip edge flashing to entire roof perimeter.
  • Install new 26 GA galvalume valley metal in all valleys.
  • Install 26 GA galvalume kitchen and dryer vents.
  • Install 26 GA eave closure metal.
  • Install new lead flashing around all plumbing stacks.
  • Install a new tile roof system with foam adhesion and or two screw fastener application system as per manufacturer specifications.
  • Provide (2) year workmanship warranty on tile application.
  • Provide manufacturers warranties.

Gutter Install Scope Of Work:

Provide labor and material to complete the following:

  • Remove and dispose of the existing gutters and downspouts.
  • Install up to 205LF of new desert sand 6″ aluminum seamless gutters with wedges.
  • Install up to (6) downspouts, (3) small downspouts, (15lf) splash guards, (4) miters, (4lf) of kickout extensions to match the existing layout.
  • Jobsite will be cleaned of all work-related debris upon completion.

Exterior Paint Scope Of Work:

  1. TRENCH AROUND PERIMETER OF HOME 1 TO 3 INCHES.
  2. PRESSURE WASH EXTERIOR FREE OF DIRT AND FOREIGN MATERIAL
  3. APPLY ONE COAT OF MASONRY SEALER TO STUCCO SURFACES
  4. SEAL MASONRY CRACKS, IF PRESENT, WITH ELASTOMERIC PATCHING COMPOUND
  5. INSPECT CAULK AT WINDOWS AND DOORS, IF DETERIORATED REMOVE AND REPLACE AS NEEDED
  6. APPLY ONE COAT OF SW DURATION SATIN PAINT, USING BRUSH AND ROLL TECHNIQUE, TO STUCCO WALLS, CEILINGS, FASCIA, SOFFIT, BANDS & TRIM
  7. APPLY ONE COAT OF SW DURATION SEMI-GLOSS PAINT TO THE EXTERIOR SIDE OF ENTRY & GARAGE DOORS
  8. A 10-year limited labor and materials warranty will be issued by Sherwin Williams.

Tile Roof Replacement, Gutter Installation, and Exterior Repaint For Ft. Myers Home

At First Service, we are blessed with the opportunity to work with many amazing clients. This home in Fort Myers, FL is no exception. The new homeowners within the Gateway community wanted a new look for their home, and chose our company to help. Our roofing division replaced the home’s damaged roof with a new Boral tile roof using their Barcelona 900 tile in their mountain blend colorway. Additionally, our team also installed new 6″ white aluminum seamless gutters to properly divert water off of the home’s roof. Once complete with the roof and gutter system, our painting division stepped in using Sherwin Williams premium paint products and repainted the exterior of this beautiful home.

This project turned out great and our client’s new home certainly increased its curb appeal. What a beautiful home!

Special Materials:

  • Tile Manufacturer: Boral
  • Style (Profile): Barcelona 900
  • Color: Stone Mountain Blend
  • Drip Edge Color: Grey
  • EXTERIOR REPAINT PAINT MANUFACTURER: SHERWIN WILLIAMS PAINT PRODUCTS
  • PRIMER: LOXON MASONRY CONDITIONER
  • STUCCO SURFACES, CEILINGS: SW DURATION SATIN
  • DOORS: SW DURATION SEMI-GLOSS

Re-Roof Scope Of Work:

Provide permit, labor, and materials to complete the following:

  • Remove existing tile and underlayment and dispose of in accordance with local code.
  • Inspect existing decking. Damaged or deteriorated decking will be replaced on a unit price basis.
  • Re-nail decking to meet hurricane mitigation code.
  • Install tile underlayment to entire roof surface.
  • Install new 26 GA pre-painted drip edge flashing to entire roof perimeter.
  • Install new 26 GA galvalume valley metal in all valleys.
  • Install 26 GA galvalume kitchen and dryer vents.
  • Install 26 GA eave closure metal.
  • Install new lead flashing around all plumbing stacks.
  • Install a new tile roof system with foam adhesion and or two screw fastener application system as per manufacturer specifications.
  • Provide five (5) year workmanship warranty on tile application. Provide manufacturers warranties.

Gutter Installation Scope Of Work:

Provide labor and material to complete the following:

  • Install new 120 LF 6″ white aluminum seamless gutters around the entire perimeter eave of the house.
  • Install “3” new white downspouts in locations approved by the homeowner.
  • Install “2” corner strip miters, and “2” outside miters.
  • Install “2” splashed guards, one on each inside corner at the base of each roof valley.

Exterior Paint Scope Of Work:

  1. TRENCH AROUND PERIMETER OF HOME 1 TO 3 INCHES.
  2. PRESSURE WASH EXTERIOR FREE OF DIRT AND FOREIGN MATERIAL
  3. APPLY ONE COAT OF MASONRY SEALER TO STUCCO SURFACES
  4. SEAL MASONRY CRACKS, IF PRESENT, WITH ELASTOMERIC PATCHING COMPOUND
  5. INSPECT CAULK AT WINDOWS AND DOORS, IF DETERIORATED REMOVE AND REPLACE AS NEEDED
  6. APPLY ONE COAT OF SW DURATION SATIN PAINT, USING BRUSH AND ROLL TECHNIQUE, TO STUCCO WALLS, CEILINGS, FASCIA, SOFFIT, BANDS & TRIM
  7. APPLY ONE COAT OF SW DURATION SEMI-GLOSS PAINT TO THE EXTERIOR SIDE OF ENTRY & GARAGE DOORS

Hilton Garden Inn Commercial Exterior Repaint

Close to the Lakeland airport, off of Route 570, this hotel wanted to transform the exterior of their facility to improve its curb appeal. Our company was hired to do just that! Once contracted, our painting division went to work to complete a full exterior repaint of the hotel just in time for Summer and incoming guests of the hotel. We used the finest Sherwin Williams paint products to produce a vibrant, deep colorway across the building. We love the colors chosen and are thrilled with how this commercial paint project turned out!

Project Information:

  • PAINT MANUFACTURER: SHERWIN WILLIAMS PAINT PRODUCTS
  • PRIMER: LOXON MASONRY CONDITIONER CLEAR
  • STUCCO SURFACES: SW SUPER PAINT SATIN
  • DOORS: SW SUPER PAINT SEMI-GLOSS

EXTERIOR PAINT SCOPE OF WORK:

  1. TRENCH AROUND PERIMETER OF BUILDING 1 TO 3 INCHES.
  2. PRESSURE WASH EXTERIOR FREE OF DIRT AND FOREIGN MATERIAL
  3. APPLY A CONSISTENT COAT OF SEALER TO ALL SURFACES TO ENSURE FINISH COAT HAS PROPPER ADHESION TO EXSISTING SURFACES.
  4. CAULK WHERE NECESSARY AROUND DOORS, WINDOWS, AND J CHANNEL. SEAL ANY CRACKS DUE TO EXPANSION AND SHRINKING FOR THE EXTERIOR ELEMENTS, AS NEEDED, WITH ELASTOMERIC PATCHING COMPOUND
  5. APPLY A CONSISTENT COAT OF FINISH TO ALL PREVISLY PAINTED SURFACES (HARDY BOARD SURFACES). WALLS AND EXTERIOR SIDE OF PREVIOSOULY PAINTED DOORS.
  6. COLORS TO MATCH EXSISTING.

Fort Myers Tile Roof Replacement & Repaint

Our office recently had the pleasure of serving the needs of a wonderful customer within the Gateway Greens community in Fort Myers Florida. Upon being contacted our team visited the residence to perform a roof inspection. With extensive damage on the roof, it was later determined that Hurricane Irma was the root cause of these damages and in order to properly repair, the home would need to receive a complete roof replacement. Once the project was approved we went to work removing the existing tile roof. Following the removal of the tile and installation of the appropriate underlayment, our team installed Boral’s Barcelona 900 tile in their gold dust color. Our team completed the roof and installed a new aluminum seamless gutter system as well to finish the project.

After our roofing team was complete, our painting division mobilized and completed a full exterior repaint using Sherwin Williams paint products. The end result turned out amazing and our customer’s selections beautifully transformed the exterior of this home!

Special Materials:

  • Tile Manufacturer: Boral
  • Style (Profile): Barcelona 900
  • Color: Gold Dust
  • Drip Edge Color: White

Re-Roof Scope Of Work:

Provide permit, labor, and materials to complete the following:

  • Remove existing tile and underlayment and dispose of in accordance with local code.
  • Inspect existing decking. Damaged or deteriorated decking will be replaced on a unit price basis.
  • Re-nail decking to meet hurricane mitigation code.
  • Install tile underlayment to entire roof surface.
  • Install new 26 GA pre-painted drip edge flashing to entire roof perimeter.
  • Install new 26 GA galvalume valley metal in all valleys.
  • Install 26 GA galvalume kitchen and dryer vents.
  • Install 26 GA eave closure metal.
  • Install new lead flashing around all plumbing stacks.
  • Install a new tile roof system with foam adhesion and or two screw fastener application system as per manufacturer specifications.
  • Provide five (5) year workmanship warranty on tile application.
  • Provide manufacturers warranties.

Gutter Installation Scope Of Work:

Provide labor and material to complete the following:

  • Remove and dispose of the existing gutters and downspouts.
  • Install up to 60LF of new white 6″ aluminum seamless gutters.
  • Install up to (3) downspouts to match existing layout.
  • Jobsite will be cleaned of all work-related debris upon completion.

Exterior Repaint:

  • PAINT MANUFACTURER: SHERWIN WILLIAMS PAINT PRODUCTS
  • PRIMER: LOXON MASONRY CONDITIONER
  • STUCCO SURFACES: SW SUPER PAINT SATIN
  • DOORS: SW SUPER PAINT SEMI-GLOSS
  1. TRENCH AROUND PERIMETER OF HOME 1 TO 3 INCHES.
  2. PRESSURE WASH EXTERIOR FREE OF DIRT AND FOREIGN MATERIAL
  3. APPLY A CONSISTENT COAT OF MASONRY SEALER TO STUCCO SURFACES
  4. CAULK WHERE NECESSARY AROUND DOORS, WINDOWS, AND J CHANNEL. SEAL MASONRY CRACKS, AS NEEDED, WITH ELASTOMERIC PATCHING COMPOUND
  5. APPLY A CONSISTENT COAT OF FINISH PAINT TO STUCCO WALLS AND EXTERIOR SIDE OF ENTRY & GARAGE DOORS

 

Condo Association Roof Replacement, Gutter Installation, and Re-Paint

Located in beautiful Cape Coral Florida, the Victoria Harbor Condominium association had contacted our office to repair damage that their facility experienced during Hurricane Irma. Following an inspection it was determined that the storm had caused extensive damage to the waterfront roofing structure resulting in a need for a complete roof replacement. Once approved, our roofing division went to work removing the existing roof and replacing it with new Eagle Malibu tile in their Riviera color. Once completed, our gutter and painting divisions stepped in to help give the building a beautiful new look. The finished product turned out amazing and our client couldn’t be happier with how everything turned out!

Special Materials

  • Tile Manufacturer: Eagle
  • Style (Profile): Malibu
  • Color: Riviera
  • Drip Edge Color: White

Re-Roof Scope Of Work

Provide permit, labor, and materials to complete the following:

  • Remove existing tile and underlayment and dispose of in accordance with local code.
  • Inspect existing decking. Damaged or deteriorated decking will be replaced on a unit price basis.
  • Re-nail decking to meet hurricane mitigation code.
  • Install tile underlayment to entire roof surface.
  • Install new 26 GA pre-painted drip edge flashing to entire roof perimeter.
  • Install new 26 GA galvalume valley metal in all valleys.
  • Install 26 GA galvalume kitchen and dryer vents.
  • Install 26 GA eave closure metal.
  • Install new lead flashing around all plumbing stacks.
  • Install a new tile roof system with foam adhesion and or two screw fastener application system as per manufacturer specifications.
  • Provide five (2) year workmanship warranty on tile application.
  • Provide manufacturers warranties.
  • Fabricate and install 24-gauge Kynar painted metal to all parapet walls for metal roof repair.
  • Cap to match building layout.
  • Attach with 5v neoprene screws. 1 foot on center along each side. This metal cap will provide a lifetime of protection to the top of the parapet walls.

Provide labor and material to complete the following gutters:

  • Remove and dispose of the existing gutters and downspouts.
  • Install up to 25LF of new white 6″ aluminum seamless gutters on the first story.
  • Install up to 135LF of new white 6″ aluminum seamless gutters on the second story.
  • Install up to (4) 2-story downspouts, (1) 1-story downspout, (5) miters to match the existing layout.
  • Jobsite will be cleaned of all work-related debris upon completion.

 

Exterior Repaint For Fort Myers Home Completed

Our painting division recently completed an exterior repaint project for a homeowner in Fort Myers Florida. Our roofing division was in the area completing a tile roof job across the street from this homeowner’s residence, and they were so impressed they contacted our company to repaint the exterior of their home. Once our client completed their color selections, we went to work prepping the home for paint prior to completing the final finish. The end result turned out great, and our customer couldn’t be happier!

Special Materials:

  • Paint Manufacturer: Sherwin Williams Paint Products
  • Primer: Loxon Masonry Conditioner
  • Stucco Surfaces: SW Duration Satin
  • Doors: SW Duration Semi-Gloss

Scope Of Work For Exterior Repaint:

  1. Trench around perimeter of home 1 to 3 inches.
  2. Pressure wash exterior free of dirt and foreign material, no bleach used, as requested.
  3. Apply one coat of masonry sealer to stucco surfaces.
  4. Caulk where necessary around doors and windows. Seal masonry cracks, as needed, with elastomeric patching compound
  5. Apply one coat of SW Duration Satin Paint, using brush and roll technique, to stucco walls, ceilings, bands, and trim.
  6. Apply one coat of SW Duration Semi-gloss paint to the exterior side of entry and garage doors.
  7. A 10-year limited labor and materials warranty issued by Sherwin Williams.

Gulf Harbour Yacht & Country Club Home Roof Replacement

Our roofing division recently had the pleasure of serving a wonderful homeowner within the Gulf Harbour community in Fort Myers Florida. This particular home had experienced damage as a result of Hurricane Irma and required a complete tile roof replacement to properly repair. In addition to the re-roof, we also installed a new gutter system for the home. Our customer chose Boral Tile’s Saxony 900 Split Slate tile in their Coconut White Antique color. This tile beautifully accented the home and instantly provided a spectacular curb appeal.

Following the completion of the project, the homeowner also elected to have our team paint the shutters to match the garage on the home. We love how this project turned out, and our customer can rest easy knowing that their residence is protected with a new roof installed by First Service!

Special Materials:

  • Tile Manufacturer: Boral
  • Style (Profile): Saxony 900 Split Slate
  • Color: Coconut White Antique
  • Drip Edge Color: White

Re-Roof Scope Of Work:

Provide permit, labor, and materials to complete the following:

  • Remove existing tile and underlayment and dispose of in accordance with local code.
  • Inspect existing decking. Damaged or deteriorated decking will be replaced on a unit price basis.
  • Re-nail decking to meet hurricane mitigation code.
  • Install tile underlayment to entire roof surface.
  • Install new 26 GA pre-painted drip edge flashing to entire roof perimeter.
  • Install new 26 GA galvalume valley metal in all valleys.
  • Install 26 GA galvalume kitchen and dryer vents.
  • Install 26 GA eave closure metal.
  • Install new lead flashing around all plumbing stacks.
  • Install a new tile roof system with foam adhesion and or two screw fastener application system as per manufacturer specifications.
  • Provide five (5) year workmanship warranty on tile application.
  • Provide manufacturers warranties.

Gutter Installation Scope Of Work:

Provide labor and material to complete the following:

  • Remove and dispose of the existing gutters and downspouts.
  • Install up to 440LF of new white 6″ aluminum seamless gutters with wedges on the first story.
  • Install up to (12) downspouts, (13) splash guards, (27) miters to match existing layout.
  • Jobsite will be cleaned of all work-related debris upon completion.

Paint Scope Of Work:

Provide permit, labor, and materials for the below mentioned project:

  1. Clean Florida shutters of all dirt and debris
  2. Lightly sand Florida shutters
  3. Paint all 10 Florida shutters with super paint and exterior satin to match front garage

 

Master Bathroom Remodel And Paint Project In Cape Coral

With decades of paint and interior finishing experience, many Southwest Florida residents turn to First Service with their remodeling needs. Our office recently completed a master bathroom remodel for a wonderful client in Cape Coral Florida. We removed the existing bathtub, deck, and tile in the bathroom. Additionally, our team also removed tower on the shower walls and prepared the area for our customer’s requested modifications. The shower wall was enlarged and the drain and supply lines were adjusted as needed once the wall was framed. Our team then proceeded to install a new freestanding tub and fixture, completed tile work in the shower area and floor, drywalled the walls accordingly, and painted the bathroom based on our customers selections.

This remodeled bathroom turned out great and our customer couldn’t be happier with the finished product.

Scope Of Work:

Provide labor and materials, except noted, for the below mentioned project:

  • Prep area where work is to be performed, lay Ram Board as needed to protect floor.
  • Demo tub, tub deck, tile surround including walls at water closet, and knee wall.
  • Demo tile on shower walls and floor.
  • Demo fixed glass at shower wall, fill in with proper framing as needed.
  • Enlarge opening into shower, size to be determined in field.
  • Adjust drain and supply lines as needed to install customer supplied freestanding tub and fixture.
  • Build 4′ knee wall at water closet.
  • Install customer supplied freestanding tub and fixture.
  • Install customer supplied tub splash guard wall tile, 50 sq. ft.
  • Tile remaining floor with customer supplied tile to match existing. Customer has on site.
  • Install two new can lights into shower tying into existing switch.
  • Rework plumbing in shower as needed for two shower heads on opposite wall, valve to be in original location.
  • Trench shower drain to accept linear style drain in existing location.
  • Construct two niches in wall underneath new shower heads.
  • Install customer supplied shower fixtures / valve.
  • Install customer supplied tile foot shelf, shower floor and wall tile, 175 sq. ft. wall tile and 32 sq. ft. floor tile.
  • Frame in shelf above linen, match texture to existing as close as possible.
  • All new drywall not tiled, to match existing wall texture as best as possible.
  • Paint entire bathroom walls, color to be determined.
  • Install new baseboard where tile was removed, match to existing, First Service to supply.
  • Note: Trench shower drain to accept linear style drain at end of shower and re-slope for proper drainage

Residential Painting Project For North Fort Myers Home

We were recently contracted by a homeowner in the Moody River area that was looking to touch up their existing residence in preparation for the holidays. Our painting division carried out the customers wishes to refine and paint areas of the kitchen and dining room. The end result turned out great and we were happy to assist the homeowner by providing some old-fashioned touch ups to this beautiful home!

Special Materials:

  • Sherwin Williams Oil-Based Primer
  • Sherwin Williams Master hide Flat

Scope Of Work:

Provide labor and materials for the below mentioned project:

Kitchen/Dining Room Ceiling

  1. Cover all areas with painter’s plastic and runners.
  2. Sand down area where new kitchen appliances are hanging above island.
  3. Prime area that is stained from upstairs leak with Sherwin Williams Oil-Based Primer.
  4. Paint entire ceiling with Sherwin Williams Master hide Flat.
  5. Upon completion the job site will be cleaned of all work-related debris.

Provide permit, labor, and materials for the below mentioned project:

  1. Case the sill of nine (9) interior opening, match existing windowsill casing as best as possible.
  2. Prime casing prior to install, caulk, and touch up paint on casing after install.
  3. Install one (1) customer supplied ceiling fan, existing circuit.
  4. Install transfer switch for 6500KW generator on outside wall back side of electrical panel.