For a condominium board, the Phase 2 milestone report is the document that turns an inspection into a construction project with a clock on it. Here is the sequence, and where a general contractor fits.
The clock
Under Florida’s SB 4-D (2022) as revised by HB 913 (Chapter 2025-175, effective July 1, 2025), a Phase 1 milestone inspection that finds substantial structural deterioration triggers a mandatory Phase 2. Once your local building department receives the Phase 2 report, repairs must begin within 365 days. Buildings reaching 30 years in 2026 (25 where the local agency requires it) face a December 31, 2026 deadline for the inspection itself, and a Structural Integrity Reserve Study completed alongside it carries the same date. Associations that previously waived reserves have been required to fund SIRS reserves since January 1, 2026.
What is usually in the report
Most Southwest Florida Phase 2 reports identify the same stack of items: spalling and delaminated concrete on balcony edges and walkways, corroded reinforcing steel, failed waterproofing and expansion joints, corroded aluminum railings, and a building envelope repaint that has to happen after the concrete work. Occasionally a roof or window package rides along.
Four contractors or one
Boards traditionally bid that list to four trades: a concrete restoration company, an aluminum shop, a waterproofing specialist and a painter. That means four bids, four schedules, four certificates of insurance, and four crews sequencing around each other on an occupied building. A general contractor that self-performs all of those trades prices the engineer’s report as one scope, under one contract, one project manager and one certificate of insurance.
What to send
- The engineer’s Phase 2 report (or SIRS) — it is the scope document.
- The property address and the management contact.
- Any prior repair records and the 40-year recertification report if one exists.
We walk the building against the report with your engineer or property manager, and return a written, line-item proposal the board can put in front of owners — with phasing options if the budget needs them. Send us your engineer’s report.
Confirm your building’s deadline with your local building department and association counsel; local agencies can add requirements.