Our office was recently contacted by a Cape Coral homeowner with a need to service their home’s 27 year old roof. Our office worked with the homeowner to remove the existing roofing structure to complete a roof replacement using GAF’s Timberline HDZ 130 mph rated asphalt shingles. These shingles will ensure that the home is protected for many storm seasons to come! The roof comes with a 2 year workmanship warranty as well as a GAF system plus 50 year non-prorated warranty which applies to any GAF material installed on the roof.
Special Materials:
- GAF Weather Watch Mineral-Surfaced Leak Barrier Peel & Stick, self-adhered shingle underlayment
- Leak Barrier MS300 Ice and Water Armor Self-Bond Peel & Stick, self-adhered shingle underlayment
- GAF Pro-Start starter shingle
- 130 mph GAF Timberline HDZ shingles
- GAF Seal A Ridge Hip & Ridge Cap Shingles
- GAF Cobra Rigid Vent3 Exhaust Vent system
Scope Of Work:
Provide permit, labor, and materials to complete the following:
- Remove existing layers of shingles, underlayment, fasteners and dispose of in First Service dumpsters.
- Inspect the condition of existing decking, flashing, and fascia board for their suitability of re-use. Any damaged or deteriorated materials will be replaced on a unit price or time and material basis. See disclaimer.
- Re-nail existing plywood roof deck to meet current Florida Building Code.
- Furnish and install (1) layer of GAF Weather Watch Mineral-Surfaced Leak Barrier Peel & Stick, self-adhered shingle underlayment, applied direct to plywood roof deck in all valley and penetration locations.
- Furnish and install (1) layer of Leak Barrier MS300 Ice and Water Armor Self-Bond Peel & Stick, self-adhered shingle underlayment, applied direct to plywood roof deck.
- Furnish and install new 26 GA – 16″ – Mill (50′) galvalume valley metal in all valleys. Note: We use a closed valley detail.
- Install 26 GA galvalume kitchen and dryer vents.
- Furnish and install drip edge fabricated from 26-gauge steel with a baked enamel finish. Standard color to be selected by Building Representative.
- Furnish and install GAF Pro-Start starter shingle at all eave/rake locations.
- Furnish and install 130 mph GAF Timberline HDZ shingles, nailed with (6) nails per shingle, to plywood decking. Color to be selected by Building Representative.
- Furnish and install GAF Seal A Ridge Hip & Ridge Cap Shingles at all hip and ridge locations. Color to match field shingle color.
- Furnish and install a GAF Cobra Rigid Vent3 Exhaust Vent system at applicable ridge lines.
- Furnish and install new lead pipe boots where existing pipes penetrate the roof surface.
- First Service will provide 2-year workmanship warranty and a GAF SYSTEM PLUS 50 YEAR NON-PRORATED WARRANTY ON ANY GAF MATERIAL ON THE ROOF. Stain Guard algae protection and 10-year limited warranty against blue-green algae discoloration available only on shingles sold in packages bearing the StainGuard® logo.